1.0 release timeline (was Re: QA Plans for 1.0)

Colin Clark colin.clark at utoronto.ca
Tue Mar 3 15:21:39 UTC 2009


Hi everyone,

Let's talk about the timing for our Infusion 1.0 release. As a  
starting point, Justin threw these proposed dates:

On 25-Feb-09, at 11:51 AM, Justin Obara wrote:

> Possible Timeline for 1.0
> ----------------------------------
>
> Bug Parade: March 10 - 23
> Testing: March 24 - 27
> Release: March 30 - 31


I think Justin's is rightfully anticipating a wave of new features in  
1.0, and wants to make sure we have enough time to test  
comprehensively and fix any lingering bugs.

On the other hand, we're going to want to balance this with enough  
time to develop these new features. Also, let's keep in mind that  
we're anticipating an Infusion 1.1 release in April, so we'll have an  
opportunity to cycle back and fix smaller bugs or add those missing  
features then.

Off the top of my head, I'm wondering about pushing bug parade to  
March 17. Thoughts? Other suggestions?

Colin

---
Colin Clark
Technical Lead, Fluid Project
Adaptive Technology Resource Centre, University of Toronto
http://fluidproject.org